LIU Hua, LI Jun-hong, WEN Jie, YANG Wu-jiao
(School of Electrical Engineering, University of South China, Hengyang 421001, China)
Abstract: Threshold decision is an important function of nuclear instrument control system based on physical parameters threshold decision. Because the conventional decision methods lack correlation with time and conditions, by analyzing the existing methods, some optimized methods are adopted. Considering safety, those methods are improved in data processing algorithms, floating threshold with multiple values, association with specific working condition, etc. These measures improve the nuclear instrument control system in fault tolerance and fault diagnosis, especially, the shutdown number of nuclear power plant decreases.
Key words: digital control system of instrument and control (DCS I&C); data processing; threshold; monitoring; decision optimization
CLD number: TP273 Document code: A
Article ID: 1674-8042(2014)04-0079-06 doi: 10.3969/j.issn.1674-8042.2014.04.015
References
[1] DONG Bin. The optimization design of the SCADA system for Ji’nan 210 t converter. Shandong Metallurgical, 2012, 34(1): 61-63.
[2] YUN Xiao-bo. Discuss the DCS's differences between domestic thermal power and nuclear power. Automation Expo, 2012, (2): 54-58.
[3] ZHOU Hai-xiang, XU Wei-ying. Third generation digital instrument control system of nuclear power unit and its localization analysis. Automation Instrument, 2010, 31(8): 61-66.
[4] WANG Ji-ning, ZHOU Ai-ping, XI Yong-xue, et al. Response time analysis and test of emergency shut down for nuclear power plant reactor protection system. Nuclear Power Engineering, 2012, 33(2): 5-10.
[5] SHENG Huang-xing, LI Hong-xia. Nuclear reactor fault early detection and on-line status monitoring methods. Nuclear Power Engineering, 2005, 26(2): 175-178.
[6] YU Wen-ge. Probabilistic risk assessment research of NPP protection system. Harbin: Harbin Engineering University, 2003.
[7] LU Cai-hua, RAO Xian-ming, ZHUANG Yun. Boron concentration monitoring in PWR nuclear power plant primary loop. Nuclear Electronics and Detection Technology, 2004, 24(3): 262-264.
[8] ZHAO Yi-qiang, YAO Qiu-guo, CHANG Yan. Rotating speed monitoring system of the main pump based on FPGA. Nuclear Electronics and Detection Technology, 2007, 27(2): 40-44.
[9] SUN Han-hong, CHENG Ping-dong, MIAO Hong-xing, et al. The third generation of nuclear power technology AP1000. Beijing: China Electric Power Press, 2010.
[10] YUAN Bing, LIU Cai-xue, HUANG Wen-lou. Analysis and research of fuel element cladding damage monitoring methods based on floating alarm threshold. Nuclear Power Engineering, 2010, 31 (1): 102-106.
[11] SU Lin-sen. 900MW PWR nuclear power plant system and equipment. Beijing: Atomic Energy Press, 2005.
[12] YAO Jin-guo, YANG Xiao-qiang, LI Zai-peng, et al. Application of line power density and DNBR protection in tianwan nuclear power plant. Nuclear Power Engineering, 2012, 33(s1): 1-4.
核电站仪控系统阈值判决及应用
刘华, 李军红, 文杰, 阳武娇
(南华大学 电气工程学院, 湖南 衡阳 421001)
摘要:基于物理参数的仪控系统阈值判决是核电站仪控系统的重要功能。 常规阈值判决固定单一, 缺乏与时间、 工况的相关性。 通过分析已有阈值判决, 提出了在安全前提下采用阈值判决优化, 在数据处理、 阈值浮动、 与工况相关联等方面作出改进, 提升了仪控系统的容错、 故障诊断能力, 降低了停堆次数。
关键词:数字化仪控系统; 数据处理; 阈值; 监测; 判决优化
引用格式:LIU Hua, LI Jun-hong, WEN Jie, et al. Threshold decision for instrument control system and its application in nuclear power plant. Journal of Measurement Science and Instrumentation, 2014, 5(4): 79-82. [doi: 10.3969/j.issn.1674-8042.2014.04.015]